The road to opening day

The equipment is in Bulgaria. Only the install is left.

For two and a half months we tracked this container from Qingdao. No more guessing: it is in Burgas, every remaining step is booked, and we open on 20 November. Here is what is left — and exactly how long it takes.

Estimated opening

20 November 2026

The date is confirmed — the container is in Burgas and every step from here is scheduled.

To opening 3d 07h 03m 48s
The journey took 74d 16h 56m 11s
To the gym 0d 07h 03m 48s
Progress 95.8% of the way
At sea 64 days
We are here
6 Nov
Customs 10 days
We are here
16 Nov
Transport 1 day
We are here
17 Nov
Install 3 days
We are here
20 Nov
  1. 01

    On the water

    Done

    The long part. The container moves on the carrier’s schedule — the date drifts a day or two either way with the weather and canal traffic.

    Window
    3 Sep → 6 Nov
    Duration
    64 days
  2. 02

    Burgas customs

    Done

    Paperwork and release of the container. It landed on 6 November and leaves for Pazardzhik on the 16th.

    Window
    6 Nov → 16 Nov
    Duration
    10 days
  3. 03

    Burgas → Pazardzhik

    Right now

    The truck leaves Burgas on 16 November and on the 17th the equipment is at the gym door.

    Window
    16 Nov → 17 Nov
    Duration
    1 day
  4. 04

    Installation

    Up next

    Unpacking, assembling and placing every machine where it belongs — from the 17th to opening day on 20 November.

    Window
    17 Nov → 20 Nov
    Duration
    3 days

The shipment

Strength zone and free weights

MSC · CORU2708568 · 1 × 20′ Dry Standard · 78 packages · 10,303 kg

Qingdao, China Ningbo, China Shekou, China Singapore Tekirdag, Türkiye Burgas
Arrived in Burgas — the sea leg is over
Departed China
3 September 2026
Arrived in Burgas
6 November 2026
Route
Qingdao, China → Burgas
Data verified on
13 November 2026

The sea legs

The container changed ships three times before reaching Burgas. Here is who carried it, and how far — click a name if you are curious where that ship is now.

  1. MSC IRINA GJ634W Completed

    Qingdao, China → Ningbo, China

    Departure: 3 Sep (confirmed) · Arrival: 11 Sep

  2. MSC OSCAR GT635W Completed

    Ningbo, China → Tekirdag, Türkiye · via Shekou, China (20 Sep–21 Sep), Singapore (30 Sep–2 Oct)

    Departure: 19 Sep · Arrival: 25 Oct

  3. MSC PROSPERITY II DA645A Completed

    Tekirdag, Türkiye → Burgas

    Departure: 5 Nov · Arrival: 6 Nov

Per MSC’s schedule, verified on 13 November 2026. The counters and the position move live.

Where this date comes from

  1. The container has been in Burgas since 6 November — that is a fact, not a forecast.
  2. Customs clearance finishes and it leaves for Pazardzhik on 16 November.
  3. On 17 November the equipment is in the gym.
  4. Three days of installation — and on 20 November we open.

The sea leg is over, so this is no longer a forecast — it is a booked schedule.